ENERGY CHINA GPEC Obtained the FYI for Medan Project in Indonesia
Date:2017-06-22 VisitCount: Font size:[ L M S ]
On June 19th, 2017, China Energy Engineering Group Guangdong Power Engineering Co., Ltd.(ENERGY CHINA GPEC) obtained the First Year Inspection(FYI)  certificate for Unit 1# of Medan Coal-fired Power Plant Project in Indonesia (Medan Project). It is the end of the project site construction. 

The Unit 1# of Medan Project was awarded the Take-over Certificate (TOC) issued by the Owner on 20th August 2015. According to the main contract, it is the warranty period that about one year after TOC. When the warranty expires, the general contractor will organize overhaul. While the overhaul was done, and approved by the owner’s supervisors, the FYI certificate would be awarded.

It is August 2016, the warranty period was ended. During the preparation of overhaul, in order to ensure the power supply of Sumatera Utara province, the Owner asked for postpone the overhaul. Therefore, the actual overhaul started on March 13th, 2017, and the end time is June 16th, 2017. After the overhaul, the project department applied for the FYI certificate in time, and obtained it in June 16th, 2017. 

It is learned that the Medan Project adopted two 200 MW condensing steam turbine generator unit characterized by ultra-high pressure, single reheat and  three-cylinder double-exhaust. After the power plant put into operation, 30% -40% of the electricity demand could be satisfied in the Sumatra Island, promoting the power and economic development of Sumatera Utara.